Tutorials › CAS Exam 8 - Advanced Ratemaking › Turning Credibility-Weighted Costs Into Relativities

CAS Exam 8 · Credibility for Classification · Tutorial 378 of 989

Turning Credibility-Weighted Costs Into Relativities

Use credibility-weighted costs to calculate and interpret class relativities on a clearly defined base.

Intermediate 10 min read

What You'll Learn

  • Calculate credibility-weighted costs before forming a relativity
  • Divide a class indication by a selected base-class cost
  • Construct a portfolio loss-cost base using exposure shares
  • Check that numerator and denominator use the same rating basis
  • Distinguish a relativity level from a change to an existing relativity

From Indicated Costs to Relativities

A credibility-weighted class loss cost is an indicated cost for a defined unit of exposure. To express that indication relative to another class or to the portfolio, divide it by the selected base cost. The result is a relativity: a dimensionless factor that describes the indicated cost difference on the chosen basis.

The calculation is simple, but its interpretation depends on two choices: which cost is in the numerator and which cost is the denominator. Both must refer to comparable coverage, exposure units, loss definitions, and cost level. A quotient of costs on different bases may be arithmetically valid but will not be a meaningful class relativity.

Definition: Let \(C_j\) be the credibility-weighted indicated loss cost for class \(j\), and let \(C_b\) be the selected base loss cost. If \(C_b>0\), the indicated relativity for class \(j\) to that base is $$ R_{j:b}=\frac{C_j}{C_b}. $$ The relativity is dimensionless. A value above 1 indicates an indicated cost greater than the selected base; a value below 1 indicates a lower indicated cost.

For a class with observed cost \(\widehat C_j\), credibility \(Z_j\), and collective complement \(C_j^{\mathrm{comp}}\), the credibility-weighted cost used here is

$$ C_j=Z_j\widehat C_j+(1-Z_j)C_j^{\mathrm{comp}}. $$

This is the credibility-weighted class cost: the observed class cost receives weight \(Z_j\), and its complement receives weight \(1-Z_j\). The relativity is then formed from the indicated cost, not automatically from the raw observed cost. The credibility weights and complements are treated as supplied or already selected for the rating problem; this tutorial concerns the conversion from those indicated costs to relativities.

Selecting and Interpreting the Base

A base-class relativity compares one class with a particular reference class. If class \(b\) is the base, its own relativity is \(C_b/C_b=1\), provided its indicated cost is positive. Other classes are expressed as multiples of that cost. The choice of base is a reference convention; changing the base changes the numerical relativities even though the indicated costs themselves do not change.

A portfolio relativity uses the exposure-weighted portfolio indicated cost as the denominator. If classes have exposure shares \(w_j\), where the shares are nonnegative and sum to 1, then the portfolio cost on that basis is

$$ C_{\mathrm{port}}=\sum_j w_jC_j, \qquad R_{j:\mathrm{port}}=\frac{C_j}{C_{\mathrm{port}}}. $$

The shares must represent the exposure mix corresponding to the costs. A share based on one exposure measure cannot be substituted casually for a share based on another. If the selected base cost is zero, division is undefined; if it is not positive, it cannot serve as a conventional positive loss-cost base.

Worked Example: Relativity to a Credibility-Weighted Base Class

In a hypothetical property program, a target class has an observed annual loss cost of $88, credibility \(Z=0.25\), and a complement of $104. The selected base class has an observed cost of $124, credibility \(Z=0.50\), and a complement of $100. All costs are per the same exposure unit and on the same coverage and loss basis. Calculate the target class’s relativity to the base class.

Method. First calculate each class’s credibility-weighted cost. Then divide the target indication by the base indication.

For the target class, the complement weight is \(1-0.25=0.75\). Its indicated cost is

$$ C_{\mathrm{target}} =0.25(88)+0.75(104) =22+78 =\$100. $$

For the base class, the complement weight is \(1-0.50=0.50\). Its indicated cost is

$$ C_{\mathrm{base}} =0.50(124)+0.50(100) =62+50 =\$112. $$

Therefore, the target-to-base relativity is

$$ R_{\mathrm{target:base}} =\frac{100}{112} =0.892857\ldots \approx 0.8929. $$

Check. The target indication, $100, is below the base indication, $112, so a relativity below 1 is consistent with the costs. The calculation avoids the common mistake of dividing the target’s raw observed cost of $88 by the base’s indicated cost; both costs in the quotient must be the selected credibility-weighted indications.

Why the Quotient Represents a Relative Cost

Suppose a base class has indicated loss cost \(C_b\), and a class’s indicated cost is \(C_j\). A multiplicative factor \(R_{j:b}\) applied to the base cost should reproduce the class indication:

$$ C_bR_{j:b}=C_j. $$

Since \(C_b>0\), solving this equation for the factor gives

$$ R_{j:b}=\frac{C_j}{C_b}. $$

This establishes why the ratio is the appropriate factor: multiplying the base cost by it returns the indicated class cost. It also shows why reversing the division is wrong. The quotient \(C_b/C_j\) would instead be the factor that converts the target cost back to the base cost.

Because the costs have matching units, those units cancel. For example, dividing dollars per vehicle-year by dollars per vehicle-year gives a dimensionless relativity. If the numerator is per vehicle-year and the denominator is per policy-year, the units do not cancel; first put the indications on a comparable exposure basis or do not interpret the quotient as a class relativity.

Worked Example: Relativities to an Exposure-Weighted Portfolio Cost

A hypothetical fleet book has three classes with credibility-weighted annual costs of $80, $100, and $140 per vehicle-year. Their shares of vehicle-year exposure are 0.50, 0.30, and 0.20, respectively. Calculate the portfolio cost and the third class’s relativity to that portfolio cost.

Method. Use the stated exposure shares to calculate the portfolio cost, then divide the third class’s indicated cost by that result.

The shares sum to \(0.50+0.30+0.20=1.00\). Thus,

$$ \begin{aligned} C_{\mathrm{port}} &=0.50(80)+0.30(100)+0.20(140)\\ &=40+30+28\\ &=\$98\text{ per vehicle-year}. \end{aligned} $$

The third class’s portfolio relativity is

$$ R_{3:\mathrm{port}} =\frac{140}{98} =1.428571\ldots \approx 1.4286. $$

Check. The third class’s indicated cost is $42 above the portfolio cost, and \(42/98\approx0.4286\); therefore its relativity is \(1+0.4286\approx1.4286\). The key trap is miscomputing the weighted average: the contribution from the third class is \(0.20(140)=28\), so the portfolio cost is $98, not $96.

When the portfolio cost is formed from the same class indications and exposure shares, the exposure-weighted average of the resulting portfolio relativities is 1. This follows directly from the definitions:

$$ \sum_j w_jR_{j:\mathrm{port}} =\sum_jw_j\frac{C_j}{C_{\mathrm{port}}} =\frac{\sum_jw_jC_j}{C_{\mathrm{port}}} =\frac{C_{\mathrm{port}}}{C_{\mathrm{port}}} =1. $$

This is a useful arithmetic check on ratios to a portfolio base. It depends on using exactly the same exposure shares in the portfolio calculation and in the weighted check. It does not mean every class relativity is 1, nor does it make the class indications equal.

Relativity Level Is Not the Same as a Rate Change

A relativity states a class cost relative to a chosen base. It is not, by itself, a percentage increase or decrease from an existing class factor. If an existing relativity and a new indicated relativity use the same base definition, their quotient gives the multiplicative change from the old factor to the new indicated factor.

Worked Example: Converting an Indicated Cost and Comparing With an Existing Factor

A hypothetical equipment class has an observed annual loss cost of $72 per insured unit, credibility \(Z=0.60\), and a complement of $90. Its selected base class has an indicated cost of $100 per insured unit. The current target-class relativity is 0.90. All figures use the same coverage, exposure unit, and cost level. Find the indicated relativity and the multiplicative change from the current relativity.

Step 1: Calculate the target indication. The complement weight is \(1-0.60=0.40\), so

$$ C_{\mathrm{target}} =0.60(72)+0.40(90) =43.20+36.00 =\$79.20. $$

Step 2: Divide by the base indication.

$$ R_{\mathrm{indicated}} =\frac{79.20}{100} =0.792. $$

Step 3: Compare with the existing relativity. The indicated-to-current factor is

$$ \frac{0.792}{0.90}=0.88. $$

Thus, the indicated relativity is 0.792, and it is 0.88 times the current relativity, equivalent to a 12% decrease in that factor. Check. The change is \((0.88-1)\times100\%=-12\%\). The common mistake is to call 0.792 an indicated 79.2% decrease: it is a relativity level, while the change from the existing 0.90 factor is found by comparing the two factors.

Common Traps and Practical Checks

The arithmetic in a relativity calculation is usually short. Errors more often come from using the wrong cost, base, or exposure basis. Before finalizing an indication, check the following:

  • Credibility comes before the ratio. Calculate the indicated class cost from the observed cost and complement before dividing, unless the problem explicitly supplies an already credibility-weighted indication.
  • Use the selected base consistently. Do not use a base class’s observed cost when the stated denominator is its credibility-weighted cost.
  • Keep the comparison basis aligned. Match coverage, loss definition, exposure unit, and cost level in numerator and denominator.
  • Use the specified portfolio mix. A portfolio base is an exposure-weighted cost, not an unweighted average unless the exposure shares are equal.
  • Read the direction of comparison. “Class relative to base” means class cost divided by base cost.
  • Separate level from change. A relativity of 0.80 is a level relative to its base; it is a 20% change only when comparing it with a prior factor of 1.00.
Key takeaway: First determine the credibility-weighted indicated cost for each required class. Then divide the target indication by the stated positive base cost, using matching units and the specified base definition. The resulting dimensionless factor expresses relative indicated cost, not an automatic rate change.

Check Your Understanding

For each problem, calculate credibility-weighted costs before forming a relativity unless the indicated costs are supplied directly. Round relativities to four decimal places.

  1. A hypothetical class has observed cost $90, credibility 0.40, and complement $100. Its selected base class has an indicated cost of $120 on the same basis. Find the target indicated cost and its base-class relativity. (Answer: $96; 0.8000)
  2. Three classes have indicated costs of $80, $100, and $140, with exposure shares 0.50, 0.30, and 0.20. Find the portfolio cost and the third class’s portfolio relativity. (Answer: $98; 1.4286)
  3. A target class has observed cost $75, credibility 0.60, and complement $95. Its base class has an indicated cost of $100. Find the target indication and relativity. (Answer: $83; 0.8300)
  4. Two classes have indicated costs of $90 and $120 and exposure shares of 0.20 and 0.80. Find the portfolio cost and the second class’s relativity to the portfolio. (Answer: $114; 1.0526)
  5. A target class has observed cost $110, credibility 0.30, and complement $90. Its selected base indication is $130, and its current relativity is 0.80. Find the new indicated relativity and its multiplicative change from the current factor. (Answer: $96; 0.7385; 0.9231, a 7.69% decrease)
Clinical Biostats